Overview
In September 2026, West Seattle Aerie #2643 completed a full roof recover of the 2,500‑sq‑ft middle flat roof above the banquet hall. This project addressed:
- Active leaks
- Ponding water
- A failing scupper
- Mixed membrane layers
- Deteriorated flashing
- HVAC curb issues
The new roof is a PVC 80‑mil membrane system installed by Frank’s Construction / San Juan Island Roofing Division.
Before Photos


Demolition



After Photos


Project Scope
The contractor completed:
- Moisture survey and substrate preparation
- Removal of wet/damaged insulation
- Installation of PVC 80‑mil membrane
- Tapered insulation for improved drainage
- Scupper repair and enlargement
- Full parapet flashing
- HVAC curb remediation
- Penetration sealing and capping
- Cleanup, inspection, and warranty documentation
Why This Project Was Critical
The old roof was failing and causing:
- Water intrusion
- Damage to the banquet hall
- Delays to the ADA bathroom project
- Risk to the building structure
Completing this project protects the Aerie for decades to come.
Contractor Spotlight: Frank’s Construction
Frank Figueroa and his team at Frank’s Construction:
- Professional workmanship
- Careful moisture remediation
- Code‑compliant installation
- A 30‑year manufacturer warranty
- A 20‑year workmanship warranty
We appreciate their work and dedication to getting this project done before the fall rains.
Support the Aerie
This project was essential — but expensive. If you’d like to support the Aerie’s roof fund:
- Donate via Zelle: wse2643
- Drop off donations at the club
- Contact the Trustees for more information